| critical path | ||||
| subject | fact | |||
| critical path | has definition A path through a PERT chart indicating the minimum time in which it is possible to complete a project, and the tasks that, if delayed, will delay the whole project | ![]() |
| indicates the minimum time in which it is possible to complete the project | ![]() | |
| is a subtopic of 11.5 - Project Scheduling and Tracking | ![]() | |
| is computed by searching for the path through the PERT chart that has the greatest cumulative elapsed time | ![]() | |
| is a kind of subject | ![]() |