critical path
subjectfact 
critical pathhas definition A path through a PERT chart indicating the minimum time in which it is possible to complete a project, and the tasks that, if delayed, will delay the whole project2001-08-30 14:55:08.0
indicates the minimum time in which it is possible to complete the project2001-08-30 14:55:08.0
is a subtopic of 11.5 - Project Scheduling and Tracking2001-08-30 14:55:08.0
is computed by searching for the path through the PERT chart that has the greatest cumulative elapsed time2001-08-30 14:55:08.0